Feasibility Study on the Supporting Terminal Work of Fine Chemicals and Raw Materials Project of NORINCO Group

21 兵器工业集团精细化工及原料工程项目配套码头工程可研.jpg

Scale of construction:

A 20,000-DWT general cargo berth is planned to be built (to simultaneously accommodate two 5,000-DWT general cargo ships; the hydraulic structure is designed to accommodate a 50,000-DWT bulk cargo ship and transport overweight and oversize cargos).

Three 10,000-DWT chemical berths, one 30,000-DWT refined oil and chemical berth, one 50,000-DWT refined oil and chemical berth (to simultaneously accommodate two 5,000-DWT oil product carriers) and one 100,000-DWT refined oil berth is planned to be built.

The berth shoreline and the land-based pipe gallery will cover a total length of 1,643 m and 1602.6m respectively.

The total handling capacity of berths is 10,608,000 t/a (9,608,000 t/a for liquid bulk cargos and 1,000,000 t/a for solid general cargos).