Master Planning of the "13th Five-Year" Construction of the Key Fishery Port, Dalian

According to standards,15 central fishery ports (including 3 new ones) of Dalian are build and improved.
It is proposed to build terminals with length of 8.2km, a breakwater and wharf with length of 3.4km, a breakwater with length of 18.8km, a revetment with length of 11.1km,an approach bank with length of 1.7 km, to reinforce the original dam with length of 1.8 km, and to construct ancillary facilities including refrigeration plant, trading market, processing plant and law enforcement office building, etc.